Those ranges come from Fixr’s national guide to kitchen remodel timelines. Your own schedule depends on the scope you choose, how early every selection is locked, and how quickly your city or county reviews the permit.

The surest way to shorten a kitchen remodel is to finish deciding before demolition starts. Our kitchen remodeling team builds each schedule from the approved design and the order dates. What the work costs is in the kitchen remodel cost guide.

How long each phase of a kitchen remodel takes

These are national durations for a typical kitchen. The construction phases run back to back, because each trade needs the one before it to finish.

How long each phase of a kitchen remodel takes
PhaseTypical timeWhat sets the paceSource
Design and selectionsA few days to 3 weeksWhether an engineer or a custom cabinet maker is involved3
Permit review1 to 2 weeks, sometimes longerYour city or county's review queue3
Cabinet delivery1 to 2 weeks for stock, 4 to 8 weeks for semi-custom, 3 to 6 months for customThe cabinet line you choose3
Demolition1 to 3 weeksDebris removal, and any mold, lead or asbestos found3
Rough plumbing and electrical2 to 4 daysWhether lines move, then the inspection3
Flooring1 to 3 daysSubfloor repairs add a day or two3
Cabinet installation2 to 3 daysThe delivery date3
Countertops2 days to a week after the cabinetsTemplating starts only once the cabinets are set3
BacksplashA couple of daysWall preparation3
Paint, fixtures and appliances1 to 3 weeksAppliance delivery dates3

Add the construction rows, plus the insulation, drywall and inspection waits the table leaves out, and a kitchen that keeps its layout lands in Fixr’s range of 6 to 12 weeks. The design, permit and cabinet rows come first, and they can overlap: cabinets are often in production while the permit is in review.

The figures are national. Tampa Bay schedules move with local permit review times and with how busy the trades are, so read the table as a sequence, not a promise.

Three scopes, three different clocks

The single biggest factor in a kitchen remodel timeline is how much of the room changes, from a cosmetic refresh to a complete kitchen remodel with a new layout.

  1. 1. Cosmetic refresh: about 1 to 2 weeks

    Paint or reface the cabinets, change the hardware, faucet and lighting, and add a backsplash. The layout stays.

    Hillsborough County lists cabinet work, painting, tile and floor coverings as work that typically needs no permit, so there is no review to wait for. A new circuit or a moved fixture changes that, so check with your own city or county.

  2. 2. Same layout, everything new: about 6 to 12 weeks of construction

    New cabinets, counters, flooring and appliances, with the sink, range and refrigerator staying roughly where they are.

    Plumbing and electrical work bring a permit and inspections. Cabinet lead time is the biggest variable.

  3. 3. New layout: about 3 to 8 months from start to finish

    Moving the sink or range, opening a wall, or adding an island with a sink. Fixr puts work like this, or a kitchen with custom cabinets, at 3 to 8 months.

    A load-bearing wall may need an engineer’s design before the permit. In a house on a concrete slab, moving a drain means cutting a trench in the slab.

What to settle before demolition

Most delays in a kitchen remodel start before the first cabinet comes out. A decision made after demolition stops every trade waiting on it.

  • Lock the layout and every selection in kitchen design: cabinets, counters, tile, sink, faucet, lighting and appliances.
  • Choose the appliances before the cabinets are ordered. The cabinet plan is drawn around each appliance’s cutout dimensions.
  • Order the long-lead items the day the design is approved. That usually means the cabinets first, then specialty tile and appliances.
  • Apply for the permit while those orders are in production, so the two waits overlap.
  • Hire one builder who answers for the whole schedule. How to choose a remodeling contractor covers what to check before you sign.
  • Plan where you will cook while the kitchen is out of service (see below).

A simple test before demolition day: every item in the new kitchen has a model number, a price and a delivery date.

Kitchen remodel steps, and why their order is fixed

Each step covers or depends on the one before it. Working out of order means tearing out finished work.

  1. 1. Protect and demolish

    Water and power to the kitchen are shut off, the rest of the house is sealed against dust, and the old kitchen comes out.

  2. 2. Rough-in

    New plumbing, wiring, gas and the range hood duct go in while the walls are open. This is the cheapest moment to add outlets or under-cabinet lighting circuits.

  3. 3. Rough inspection

    The building department inspects the rough work before anything covers it. A failed inspection holds every step after it.

  4. 4. Insulation and drywall

    The walls close, then get taped, finished and primed.

  5. 5. Flooring

    Flooring goes in before or after the cabinets, depending on the material (see the questions below).

  6. 6. Cabinets

    Cabinets are set level and fixed in place. Everything after this step is measured from them.

  7. 7. Countertops

    The fabricator templates the installed cabinets, then cuts and installs the counters.

  8. 8. Backsplash

    Tile goes up after the counters, so it sits tight on the finished surface.

  9. 9. Fixtures and appliances

    The sink, faucet and disposal are connected, the appliances are set, and the lights go on.

  10. 10. Final inspection and punch list

    The final inspection closes the permit. A walk-through then lists any touch-ups before the final payment.

Wall oven or range: decide before the cabinets are drawn

This is the appliance choice that changes the cabinet plan most. A range is one appliance, usually in a 30 or 36 inch space. A wall oven and cooktop split the job between a tall oven cabinet and a separate cooktop.

Wall oven or range: decide before the cabinets are drawn
ItemTypical national rangeSource
Freestanding range$800 to $2,0001
Slide-in rangeAbout $500 to $1,000 more than freestanding1
Single wall oven, unit only$600 to $4,7001
Double wall oven, unit only$1,200 to $5,0001
Wall oven installation$100 to $2501
Cooktop, installed$500 to $1,0002
Custom cabinet built around a wall oven$1,000 to $5,0001

The figures are national, from Fixr’s appliance cost guides updated in January 2025. The split setup usually costs more because it is two appliances plus the tall cabinet that holds the oven.

A range makes sense when

  • The kitchen has no wall space to spare for a tall cabinet.
  • You want one appliance to buy, service and replace.
  • The money is better spent on cabinets or counters.

A wall oven and cooktop make sense when

  • You want the oven at waist or eye height, so heavy pans come out without bending.
  • You want the cooktop in an island, facing the room. It still needs a hood or a downdraft to vent it.
  • You want to mix fuels or brands, such as a gas cooktop with an electric oven, without buying a dual-fuel range.

Either way, plan the landing space. The National Kitchen & Bath Association recommends at least 15 inches of counter next to or above a wall oven, and 12 inches on one side of a cooktop with 15 inches on the other.

Switching from one to the other is a layout change. Most electric wall ovens are hardwired to a junction box, an island cooktop needs new power or gas and a vent route, and the old opening needs new cabinets and counter. Settle it during design, not after the cabinet order.

Living at home while the kitchen is out

For a kitchen that keeps its layout, most households stay home and set up a temporary kitchen. For a layout change with weeks of slab or wall work, some move out for the loudest stretch.

  • Set up the refrigerator, a microwave, a coffee maker and a toaster oven or plug-in induction burner near a sink, such as in the laundry room.
  • Move everyday dishes and pantry staples there before demolition day.
  • Expect a dust barrier at the kitchen doorway and a sealed return vent while work is underway.
  • Plan easy meals for the demolition and rough-in weeks, when the kitchen has no water.

What stretches a kitchen remodel timeline

  • Changes after demolition. A new sink location or a different cabinet line resets orders, drawings and sometimes the permit.
  • Backordered cabinets or appliances. Confirm delivery dates in writing before demolition, and hold items on site once they arrive.
  • What the walls hide. Rotted subfloor under an old sink, outdated wiring or termite damage adds repair days and sometimes an extra inspection. Older houses hide more; how to renovate an old house explains.
  • Inspection slots. Each inspection waits for an open slot, and work that covers the inspected item cannot start until it passes.
  • Late cabinets. Fabricators template only after the cabinets are installed, so a late cabinet delivery moves the counters too.

The fix for most of these is the same: decide early, order early, and keep one person responsible for the schedule. A breakfast nook or a second room added to the same project brings its own steps, so plan it in the same design phase. For a remodel that reaches past the kitchen, start with how to plan a home remodel.

Kitchen remodel timeline questions

What is the difference between a kitchen remodel and a kitchen renovation?

People use the words loosely. A renovation usually means renewing what is there, such as new cabinets and counters in the same layout, while a remodel usually means changing the layout or how the room works. The difference that matters for the schedule is whether walls, drains or gas lines move, because that adds design, permit and inspection time.

Do I need a permit to remodel a kitchen in Florida?

It depends on the work, and each city or county issues permits under the Florida Building Code. Hillsborough County lists cabinet work, painting, tile and floor coverings as work that typically needs no permit, while a remodel that involves plumbing likely needs one, as do new circuits and structural changes. Ask your building department before you start, and read remodeling permits.

Should flooring go in before or after the cabinets?

It depends on the floor. Tile and glued or nailed floors can go in first, which gives a continuous floor under everything, or after, which saves material as long as the floor still runs under the dishwasher and range so they can be pulled out. Floating floors, such as most click-together vinyl plank, go in after the cabinets, because their makers do not allow cabinets to be installed on top of them.

Can I keep my existing appliances?

Yes, and it can shorten the schedule, since nothing waits on a delivery. Give the designer each appliance’s exact dimensions so the new cabinets fit them. If you plan to replace one within a few years, size the opening for the standard width you will buy next.

Will doing some of the work myself speed things up?

Rarely. Homeowner tasks such as demolition or painting have to finish exactly when the next trade arrives, or the crew waits. The work that does save time sits off the critical path: emptying the kitchen, setting up the temporary kitchen and making selections on time.

Ask for a timeline for your kitchen

Sources

  1. 1.Fixr, Oven Installation Cost (Adam Graham, updated January 31, 2025) (opens in a new tab), checked
  2. 2.Fixr, Cooktop Prices (Adam Graham, updated January 31, 2025) (opens in a new tab), checked
  3. 3.Fixr, How Long Does a Kitchen Remodel Take? (Dan Simms, January 13, 2025) (opens in a new tab), checked
  4. 4.Hillsborough County, Permits for Homeowners (opens in a new tab), checked
  5. 5.Hillsborough County, Virtual Inspections (opens in a new tab), checked
  6. 6.Consumer Reports, Cooktop and Wall Oven vs. Range (Paul Hope, February 4, 2017) (opens in a new tab), checked
  7. 7.National Kitchen & Bath Association, Kitchen Planning Guidelines with Access Standards (opens in a new tab), checked
  8. 8.Hurst Hardwoods, Spring Tech floating vinyl installation instructions, checked