One county, two permit clocks
Bathroom remodeling in Palm Harbor has no city building office to go through: its residential permits are Pinellas County’s, filed only through the county’s Accela system rather than at a counter.
More on county permits
For a bathroom that moves its drain or rebuilds its shower around a ceiling rain head, the schedule carries the county’s figure of about 14 days for a typical residential permit rather than the 0 to 2 business days it quotes for an express one. Nothing the county publishes says which bathroom scopes count as express, so a shower remodel is planned on the longer figure until the application is in. If the county treats the job as express, the work simply starts sooner.