Progress, as the city counts it
Once work is under way, a second limit takes over. The same answers say a permit also becomes invalid if the work is suspended or abandoned for six months after it started, and that work is considered to be in active progress when the permit has received an approved inspection within 180 days.
More on 180-day rule
The measure is a passed inspection on the permit, not a crew in the house. A kitchen’s inspections usually come at its two ends: the rough work, while new circuits, a moved drain or an extended gas line are still exposed, and the final, once the appliances are connected. Between them come the cabinets, the countertop template, the stone’s fabrication and setting, the backsplash and the hookups, and as a rule no inspection falls in that stretch.
That middle stretch is where a Venice kitchen spends its 180 days. A cabinet line that ships late, or a slab that cracks in fabrication and has to be cut again, stretches it, so the calendar after rough-in counts from the last approved inspection, not from demolition day.