A promise on the public record
Where a garage below that line stays a garage, the city attaches a document to it. Its floodplain page says a non-conversion agreement, signed by the owner and recorded with the Sarasota County Public Records, must be signed before a Certificate of Occupancy is granted.
More on non-conversion
An addition that comes with a garage, a new bay at the side of the house or parking under a raised wing, meets that agreement at the end: the Certificate of Occupancy for the new space waits on the owner’s signature. Once recorded, the agreement sits in the county’s public records for the property, where a later buyer’s title search can find it.
For a whole building, the city’s substantial improvement notice draws the same boundary. Once a building whose lowest floor sits under the line is substantially improved, it must be elevated, with its bathrooms, laundry rooms and electrical and mechanical equipment raised to the line or higher. Below the base flood elevation, only parking, building access and limited incidental storage may remain.